CC is permission to commence. OC is permission to occupy.

They are not interchangeable and the exact stages / conditions depend on the competent authority and project. Build the construction programme around sanctioned approvals, inspections and consultant records.

1Sanction / pre-CC conditions
→
2CC / stage permission
→
3Construction + inspection
→
4Approved amendments
→
5Completion package
→
6OC
→
7Possession + handover

Construction controls

  • Approved drawings and revision register
  • Contract scope / BOQ / specifications
  • Programme and milestone tracking
  • Quality / testing records
  • Safety and insurance controls

Commercial controls

  • Measurement / billing certification
  • Variation / change orders
  • Retention / guarantees
  • Delay / extension records
  • Budget and cash-flow updates

Completion controls

  • Consultant completion certificates
  • Applicable service / fire / lift closures
  • As-built drawings and warranties
  • OC / occupancy records
  • Defect / maintenance handover
Final handover

Keys are only one part of handover.

Plan the project records that must survive after the developer's site team leaves.

01Possession

Unit / member possession records and outstanding-item schedule.

02Technical

As-builts, manuals, warranties, test certificates and service contacts.

03Society / common

Common assets, maintenance records, accounts and governance handover as applicable.

04Title

Conveyance / transfer and property-record closure as applicable.

PDF
CC / OC / Final Handover ChecklistModel project-control checklist.